Workday Project Phases

Planning Phase
June 2019 - October 2019
- Discovery
- Project Governance
- Project Plan Development
Architect Phase
August 2019 - February 2020
Configure and Prototype Build Phase
November 2019 - May 2020
Test 6,000+ business processes Phase
October 2019 - November 2021
- End to End Testing for Cycle One (April 2020 - August 2020)
- End to End Testing for Cycle Two (September 2020 - December 2020)
- End to End Testing for Cycle Three (March 2021 - July 2021)
- Payroll Parallel Testing (July 2021 - October 2021)
Deployment Phase
December 2020 - January 2022
- MC Learns through Workday Go Live (December 2020)
- Performance Go Live (July 2021)
- HCM, Payroll, and Finance Go Live (January 2022)