Workday Project Phases

person working on laptop that shows a project

Planning Phase

June 2019 - October 2019

  • Discovery
  • Project Governance
  • Project Plan Development

Architect Phase

August 2019 - February 2020


Configure and Prototype Build Phase

November 2019 - May 2020


Test 6,000+ business processes Phase

October 2019 - November 2021

  • End to End Testing for Cycle One (April 2020 - August 2020)
  • End to End Testing for Cycle Two (September 2020 - December 2020)
  • End to End Testing for Cycle Three (March 2021 - July 2021)
  • Payroll Parallel Testing (July 2021 - October 2021)

Deployment Phase

December 2020 - January 2022

  • MC Learns through Workday Go Live (December 2020)
  • Performance Go Live (July 2021)
  • HCM, Payroll, and Finance Go Live (January 2022)
©